   The Marion County Commission took two steps forward on road improvement projects (Fuller Road, Slaughter Road) during its recent meeting and also discussed the difficulty of officials' efforts to improve J.P. Hudson Road, a portion of which has been closed for more than a year.
   Fuller Road: The commissioners accepted a bid of $112,346 from Robinson Paving for work on Fuller Road. The project includes excavation, filling ... The rest of the story.